The Stage 2 LRT team has shared the following information with us regarding imminent rock breaking work:
Please be advised that KEV will be approximately 2 to 3 weeks of rock breaking between Connaught Avenue and the OC Transpo building. KEV currently intends to begin these works this weekend working daytime only, they will continue to work daytimes until completed. At this point no night work is anticipated with this activity.
KEV has also confirmed that there will be a noise and vibration monitor installed to track these works. They also anticipate that it will be impactful for residents along Connaught and Severn.
Please share this information with your community.
If you have any questions or concerns on this project, please contact the Stage 2 LRT team directly and include us on your exchange (as appropriate).